Mayor’s Update | News from the garden city

0


Mayor Cosmo Veneziale

Sidewalks and trees in the village

At the board meeting on June 4, 2021, trustees discussed the trees and sidewalks in the village. Administrator John Delany said this has been a problem for many years and some trees belonging to the village are generating sidewalk repairs. The discussion included the mention that (legally, by local law in the village code) adjacent owners are currently responsible for sidewalk repairs, even when village tree roots are causing the damage. According to village administrator Ralph Suozzi, over a five-year period (2016-2020), the village made an average of $ 531,000 per year in repairs – around $ 200,000 for aprons / curbs and around 300 $ 000 for sidewalk repairs. The estimated influence of village tree roots is estimated to be around 50 percent, perhaps up to 60 percent of that $ 300,000, based on estimates of the paving program defined during each fiscal year, a added Mr. Suozzi. Deputy Superintendent of Public Works Domenick Stanco explained the process of surveying sidewalk slabs. The Village will continue its policy regarding the replacement of sidewalks and examine the defects of the sidewalks caused by the planting of trees in the Village, as well as the cost of these repairs to the owners.

Update on the water

Water tower: At the Old Country Road Water Tower, all welding and grinding repairs have been done. The contractor is working on repairs to the interior lining due to weld repairs, as well as the exterior bands and middle layers of the tank.

Discolored water survey: H2M has had phone conversations with residents who recently had water discoloration issues. Contacted the village to obtain a register of consumer complaints. Waiting for the history of the presence of discolored water to assess the locations.

Well 7 (aqueduct site): Construction is complete and in use. The contractor works on ordering parts for the items on the checklist. Permanent construction to be incorporated into the permanent construction of wells 8 and 12.

Wells 8 and 12 (Rockaway Avenue site): Sampling lines and drainage piping continue. Fiber cables pulled. The AOP boxes are powered on. Water flow / pressure tests are expected within two weeks. The chests should be in place next week. Installation of the peroxide tank and pads is also scheduled for next week.

Well 9 (rue Wilson site): The engineering report was submitted the week of May 3, 2021. H2M will provide the Village with a design proposal for an AOP treatment system.

Wells 10 and 11 (Clinton Road site): We are awaiting POC results for well # 10. The results will be submitted to the New York State Department of Health for operational approval. The contractor will restore the site and install the doors and soffits. H2M will prepare the preliminary elevations of the GAC building accordingly. Plantations on the site will be discussed separately.

Wells 13 and 14 (Garden City Country Club site): Video of completed work has been recorded. H2M will contact the contractor to have him complete the provisional construction.

Wells 15 and 16 (Hilton Park site): The generator was delivered to the site, the cinder block work to the upper masonry was completed, and the packaging was installed in the air stripping tower. Roofing work, placement of concrete for the decking and placement of the generator will begin. The masonry is on hold until the delivery of the poured stone for the water table.

Board meeting

The next board meeting will be held on Thursday, June 17, 2021 from 7:30 p.m. in the boardroom of the village hall and also via Zoom. The Zoom link will be posted on the Village website the day before the meeting.

Sunday Library Hours

The Garden City Public Library will be open on the following Sundays in 2021-2022:

• September 12, 19, 26

• October 3, 17, 24, 31

• November 7, 14, 21, 28

• December 5, 12, 19

• January 9, 16, 23, 30

• February 6, 20, 27

• March 6, 13, 20, 27

• April 3, 10, 17, 24,

• May 1, 8, 15, 22, 29

• June 5, 12

Update of the LIRR expansion project

In June, you’ll see crews doing the following construction activities in Garden City:

Wall construction

• Construction of the noise barrier will continue along the north side of the tracks, west of Merillon station

• Work on these wall sections will continue over the weekend throughout June.

Development of the avenue Merillon station

• The teams have started the process of commissioning and testing the new elevators at the Merillon Avenue station to ensure that all functionality and safety requirements are met. During testing and commissioning, crews will continue to lay thin bricks inside and outside the elevator buildings.

• Guardrails and guardrails are installed on the stairs and ramps on the north and south sides of the tracks.

• EJ Electric installs lighting at the station and at the platform duct along the right-of-way, on the north and south sides of the tracks

Installation of the 3rd channel

• Ballast will be installed along the south side of the right-of-way during the day to support the future installation of the third track. Once the ballast is installed, the crews will build the track between Nassau Boulevard and Herricks Road

Double-track purlins

• Double track outages are planned for the main line on June 12 and 13 and the Oyster Bay line on June 26 and 27.

To reduce the overall project schedule, the project team will use these dual track blackouts to complete other activities near the tracks.

During these weekends, residents will likely notice increased activity along the right-of-way

To ensure the restoration of rail service by Monday morning, crews will work overnight

LIRR working together The influence

• In addition to 3TC activities, you can see or hear LIRR forces working along the railway right-of-way.

• To avoid LIRR service interruptions during peak hours, LIRR works along the railway right-of-way can take place at night and on weekends.

• For more information, visit the post in the Community News section of LIRRExpansion.com

• For up-to-date LIRR service changes and / or station access changes, please visit www.MTA.info/LIRR

Walks

Enjoy Garden City-style hospitality every week this summer as Garden City Village and the Garden City Chamber of Commerce once again present the “Friday Night Walks” on Seventh Street. The festivities begin at 6 p.m. Seventh Street is closed to all traffic and parking begins at 5:45 pm. Enjoy live music and lots of activities for the kids, including balloon art and face painting. Tables and chairs will be set up on the street for additional seating and alfresco dining along Seventh Street. The dates (and themes) of the walks are as follows:

June 11: Mardi Gras

June 18: Garden City State of Mind (Billy Joel)

June 25: Saint-Patrick

July 2: Metro Series

July 9: Rock of the Ages

July 16: Shake, Rattle & Roll

July 23: Christmas in July

July 30: Back to the 80s

August 6: Sock Hop and Doo Wop

August 13: Peace, Love & Music (60s)

August 20: Frank Sinatra

August 27: Aloha Luau

September 3: Country Western

September 10: The Great Pineapple Circus

Subscribe to our email alerts

Want to stay connected to the Village and its activities? Sign up to receive email alerts through an online portal on the Garden City homepage. The link is located at the bottom right of the Village website, www.gardencityny.net. All you’ll need to do is provide your name and a valid email address to immediately start receiving non-urgent updates on local meetings and events, upcoming festivals, even town hall vacation hours. , approved solicitations and road closures. Also follow our Facebook page for daily updates, www.facebook.com/VillageofGC.



Source link

Share.

About Author

kurt watkins

Comments are closed.